Title:     Fire Door Replacement Programme
From:
  August 2019
To:         Current
Value:  £8.8m

Overview:

The replacement, installation and/or repair of fire doors for a total of c200 properties. Following the completion of the flat front entrance doors, the project then focussed on the communal and service doorsets within each block. The main services provided include:

  • Acting as Principal Contractor and Principal Designer
  • Producing a Construction Phase Plan
  • Working with Lewisham Homes to develop the programme
  • Working with Lewisham Homes to develop site specific risk assessment method statements
  • Manufacture of the fire doors, based on our survey data
  • Resident liaison including engagement meetings, appointment making, customer care and complaints handling
  • Fire door installations and repairs by FIRAS and IFC certified operatives to manufacturer guidance
  • Installation of signage in accordance with Building Regulations and Health and Safety Regulations
  • Monthly operational meetings with Lewisham Homes to review progress and performance
  • Document exchange via Microsoft SharePoint, our secure extranet